Changing project start and end dates

By Randy Del / Thursday, December 17, 2015 at 7:20 PM

When creating a new project, by default the application sets its period as 1 year. You can change that period to a longer or shorter one.

To set a new period:

  1. On the menu, select: Project > Set Calendar Period...

     
  2. Specify the new period.

     
  3. Confirm the changes by clicking ОК.

Warning! When changing a period, all transactions that do not fit in the new period will be deleted.